Searchable article text
RMTnews :: august/september 2007 :: www.rmt.org.uk
24
F
ollowing the demise of Metronet,
bringing London Underground
infrastructure work back into the public
sector is the only option if Tube upgrades
are to be put back on track.
The government was warned about the
dangers of fragmenting Tube infrastructure
along the same fault-line as the national rail
network.
They were warned that forecasts of £4.5
billion in savings over public-sector
management were fanciful, and that the PPP
would become an expensive drain on public
money.
They were warned that there was no
evidence to suggest that the private sector
could deliver more efficiently than LU.
And they were warned that the public
would be left to pick up the tab when it all
went wrong.
Transport for London itself warned that
the PPP was not value for money, was
unsafe and unmanageable and would not
properly protect the public interest.
Despite those warnings we were told that
the PPP would deliver massive
improvements funded by huge private-
sector investment and, best of all, it would
transfer financial risk to the private sector.
There is no pleasure in saying we told
you so, not least because the fall-out
threatens to undermine essential upgrades,
but the reality has been in line with the
warnings.
Massive improvements dissolved into a
huge and growing backlog of work, with
frequent engineering overruns disrupting
Tube traffic, and an unprecedented string of
potentially disastrous derailments.
PPP MYTHS DEBUNKED
The huge private investment was a myth,
with expensive private borrowing ultimately
costing the taxpayer twice as much as other
options.
But the biggest myth of all was the
transfer of risk.
Metronet’s shareholders – Atkins, Balfour
Beatty, Bombardier Transportation, EDF
Energy, RWE Thames Water – abandoned
Metronet because they couldn’t get the
public purse to underwrite their massive
cost overruns – leaving the public with a £2
billion debt, racking up interest at
commercial rates.
Metronet’s shareholders staked a modest
£350 million, dwarfed by the more than
£3.3 billion in public money pumped into
the PPP over its first three years.
Even so, the two Metronet contracts still
managed to siphon off some £127.3 million
in profit in those first three years – more
than £800,000 a week.
Recall that it cost half a billion of
taxpayers’ pounds just to draw up the
contracts, and LUL even re-imbursed the
privateers’ £275 million start-up costs. Now
we have the cost of administration,
estimated at as much as £30 million a week.
Some have suggested that Metronet is the
problem, not the PPP.
Alongside Metronet’s breathtaking
failure, Tube Lines’ performance certainly
looks better, but even if the PPP was
delivering according to the script, it would
still be delivering less than was demanded
of LUL, at massive extra cost.
Seven years ago the Industrial Society
noted that the PPP offered the prospect of a
guaranteed 15.3 per cent return on equity
for 30 years, with performance benchmarks
five per cent below those expected of
publicly owned London Underground.
MORE EXPENSIVE
The 2005 the Commons’ Transport Select
Committee reported that, even without the
costs of the Jubilee Line extension,
government expenditure on the Tube had
increased more than twentyfold, from
£44.1m in 1997-98 to £1,048 million 2004-
05.
What limited successes have been
achieved “could hardly be otherwise”,
according to TfL’s 2005 report, given the
huge sums thrown at the PPP, but overall
performance was still “not good enough”
and “less than was promised”, and “the
volume of real work out on the railway is
not consistent with the payments being
made.”
The same report noted that engineering
overruns had increased by some 35 per cent
on the first year, averaging more than one a
week.
The 2005/06 TfL report noted that LUL
had issued a Corrective Action Notice to
Tube Lines due to its “persistent poor
performance” on the Northern Line which
“was manifest in repeated track, signal and
rolling stock failures”.
Nonetheless, Tube Lines managed to
extract profits of £158.7 million in the first
three years of the PPP – more than a £1
million a week.
POOR PERFORMANCE
The astonishing thing is not that the PPP
has failed to deliver – because it was never
going to – but that Metronet, despite some
of the most generous contracts ever
designed by bean-counter man, failed to
bag its full quota of guaranteed, risk-free
profits.
The solution to this mess is obvious to
most, and even city voices are calling for
infrastructure work to be taken back in-
house under direct LUL control.
Network Rail has already shown what
can be achieved by bringing maintenance
back in-house, a move that brought
immediate benefits in reducing delays, and
which made a welcome start towards
recreating a single command structure.
It is unthinkable that Metronet’s death
throes should be allowed to result in even
more fragmentation, and we have warned
the administrator that any attempt to cut
jobs or conditions or forcibly transfer our
members will be resisted, with strike action
if necessary.
It is our members who are out there
every day trying to deliver the
improvements the Tube network desperately
needs, and that skilled workforce will still
be needed long after Metronet is forgotten.
Mayor Livingstone opposed the PPP and
now has four years’ experience of it to show
that he was right to.
LUL has warned that failure to deliver its
minimum improvements programme means
a future of delays, overcrowding,
catastrophic failures, line closures, declining
safety and massive knock-on costs.
No-one will lament the end of Metronet,
the PPP has failed and must be buried.
TIME TO BURY THE PPP