The report into the fatal
derailment of a passenger
train at Carmont,
Aberdeenshire, August 12,
2020 by the Rail Accident
Investigation Branch (RAIB) has
made 20 recommendations for
the improvement of railway
safety including the better
management of construction
activities by Network Rail and
its contractors.
In response RMT called for
an urgent rail safety summit of
the Scottish and UK
government’s, rail unions,
Network Rail, the rail
infrastructure companies and
operators to prevent another
tragedy on the railways.
RMT also called on Network
Rail to halt plans to cut
thousands of safety critical rail
jobs and for action to protect
jobs in the rail infrastructure
supply chain.
The report published
earlier this month studied the
causes of the derailment of a
passenger train at Carmont in
which the conductor Donald
Dinnie, driver Brett
McCullough and passenger
Christopher Stuchbury were
killed and six other passengers
were injured.
The union said that the
report showed that there were
systemic and structural failures
in safety caused by
fragmentation, poor
communication and
management and also the
failure of the now defunct
contactor Carillon.
RMT general secretary Mick
Lynch said that it was shocking
that although the failure of the
sub-contractor Carillion was
one of the key causes of this
tragedy the fact that the
company was now defunct
means those responsible may
not be properly held to
account.
“There were also systemic
and structural failures in
railway safety caused by
fragmentation with different
companies responsible for the
management and
implementation of safety
critical work, signalling,
operations and rolling stock.
“Ultimately risks will be
reduced by creating one
unified railway, but meanwhile
we are demanding an urgent
safety summit, between
governments, Network Rail,
Operators and the railway
infrastructure supply chain to
agree steps to ensure this type
of tragedy can never happen
again.
“And we are calling for an
immediate halt to plans by
Network Rail to cut thousands
of safety critical maintenance
jobs and guarantees that the
necessary investment in the
rail infrastructure and modern
communication systems to
keep the railways safe will take
place,” he said.
The report found that in the
morning of the accident there
was near-continuous heavy rain
at the site of the accident. As
a result, Train 1T08 derailed
because it struck debris that
had been washed out of a
drainage trench. This trench,
which had been constructed
between 2011 and 2012,
contained a perforated pipe
that had been installed as part
of a project to address a
known problem with drainage
and the stability of a cutting in
that area.
However, the drainage
system and associated
earthworks had not been
constructed in accordance with
the original design and so
were not able to safely
accommodate the water flows
that morning.
RAIB’s investigators found
that a low earth bank (bund)
had been constructed that ran
across a slope leading towards
the track. The presence of this
bund significantly altered the
flow of water such that
extreme rainfall would cause a
concentrated flow into the
steeply sloping section of
trench.
The evidence indicates that
the intensity and duration of
this rainfall would have
generated water flows into the
trench that were sufficient to
wash away the gravel fill and
the ground immediately
surrounding the trench.
CARMONT
DISASTER REPORT
Union calls for urgent safety summit and halt to job
and budget cuts to prevent more rail tragedies