MT has exposed a catalogue
of faults left behind by
contractors working on the £500
million redevelopment of
London Bridge which have been
the catalyst to the chaos and
overcrowding at the station.
Senior RMT officials have
identified the poor installation
of new track and signalling
layout, incorrect procedures
followed, dangerous corners cut,
union concerns ignored and
Network Rail engineers left to
correct contractor faults.
Meaningless and fantasy
computer models also
underestimated traffic and
footfall used to justify plans.
Works at the station have
been undertaken by a variety of
contractors and sub-contractors
with Balfour Beatty the main
firm on the track remodelling
and Costains in charge of the
overall station redevelopment.
RMT general secretary Mick
Cash said that RMT had warned
from the off that the continuing
chaos at London Bridge could
be tracked back to the
fragmentation and privatisation
of the railways with its myriad
of contractors and sub-
contractors and the drive to cut
corners and rush through
important works in the interest
of meeting financial targets and
protecting profits.
“The catalogue of faults
identified by our reps is breath-
taking and, alongside the abject
failure to listen to our members
who understand how a railway
works, shows that the
continuing chaos and
overcrowding at London Bridge
was entirely predictable.
“Even though RMT blew the
whistle on this right from the
off at no point since the pictures
of the dangerous situation
emerged have our reps and our
members been asked for their
views by the DfT and the
politicians who are posing about
claiming that they are tackling
the crisis.
“We were ignored at the start
and we are still being ignored
now and our demand for a
summit on the growing safety
and overcrowding scandal on
our transport services has fallen
on deaf ears.
“RMT will continue to expose
the truth while those responsible
offer nothing but PR stunts and
sticking plaster solutions,” he
said.
He said that the voices and
the warnings of staff on both
rail and tube were being ignored
by senior managers who the
union believes are engaged in
an orchestrated and politically-
motivated cover up of the risks
and the facts in pursuit of a cuts
agenda.
“That dangerous ignorance
has to stop before we have a
major disaster on our hands.
"We have seen too often
what happens when officials,
politicians and authorities
conspire to ignore whistle
blowers and cover up the truth.
“RMT will fight to stop that
scenario developing any further
in our transport services,” he
said.
LIFTING THE LID ON
LONDON BRIDGE CHAOS
Farce traced back to the fragmentation and
privatisation of the railways with myriad of
contractors and sub-contractors