R
MT has called for a halt to
planned cuts to Network
Rail budgets and staffing levels
after the regulator, the Office of
Rail Regulation, backed RMT’s
case that the cuts are hitting
passenger services.
The ORR, which also sets the
Network Rail budget, said that
“underspends” [ie cuts] on
maintenance work, deferred
plans to renew infrastructure,
and other factors including
engineering works overruns are
leading to severe delays for
both passenger and freight
services.
The union said that a
programme of investment and
recruitment was clearly required
in maintenance and renewals.
ORR’s analysis of rail
performance highlights that
more than half of delays on the
network are caused by problems
attributed to Network Rail cuts
that the ORR themselves have
imposed.
The ORR report revealed that
“between April and October this
year, there were more than
nearly 16,000 infrastructure
incidents across the network,
nearly five per cent more than
over the same period last year,
despite benign weather
conditions, causing almost 1.7
million minutes of delay to
trains nationally”.
This extraordinary report not
only supports everything RMT
has been saying about the
impact on rail services of cuts
to maintenance and renewals
but which also blows the lid off
the role that the ORR
themselves play in imposing
cuts, on behalf of the
government, on Network Rail.
RMT general secretary Bob
Crow said that the report made
it clear that major delays to
services were bound up with
Network Rail’s deferral of works
for parts of the rail network
such as tracks, level crossings
and electrification.
“That is a shocking
indictment on the state of
Britain’s railways while the
private train operators are
creaming off a fortune, but
worse is to come.
“Only last month the ORR
demanded a further £1.7 billion
of cuts from Network Rail from
2014, cuts which would hack
back skeleton staffing levels
and drag back maintenance and
renewals even further than the
dire conditions identified in
today’s report.
“ORR has got a nerve
complaining about the impact
of the cuts on one hand and
then doling out another bunch
with the other and this
shambles has got to stop.
“That means ending the
profiteering of privatisation and
reinvesting that hard cash
siphoned off by the private
companies back into capacity,
staffing and infrastructure.
“It also means ending the
fragmentation and waste of
“outsourcing” and sub-
contracting and bringing all the
works on our railways directly
under the control of Network
Rail,” he said.
RAIL REGULATOR ADMITS
MAINTENANCE CUTS
HAMMERING SERVICES