Searchable article text
RMT helpline 0800 376 3706 :: march 2013 :: RMTnews
12
END CASUALISATION
ON THE TRACK
RMT calls for reversal of job cuts and all
track works brought in house
Broken rails, overhead line
failures and routine safety
breaches are causing chaos on
the rail network and members
working on track maintenance
and renewals believe that the
root of the problem is staff cuts
and the casualisation of the
industry.
RMT has long-running
serious concerns over corner-
cutting and the drive for profit
at the expense of safety.
In one recent incident
reported by the union a track
worker had the fingertips from
three fingers cut off when a
high output renewals machine
went over his hand.
Other incidents raised by
RMT with Network Rail and its
contractors include a ballast
regulator operated by a single
member of staff, trollies placed
on an open running line and
near misses with staff walking
on what they believed to be
protected areas.
Increasingly, there are
problems caused by a failure to
consider, plan, establish and
then brief out to staff a simple
safe system of work (SSOW).
Staff are also undertaking work
for which they are not
competent to carry out and
workers being subjected to a
culture of fear – a fear that if
they do speak out on safety they
will not be given any further
work.
This is leading to an
underreporting of accidents and
concerns over the safety
implications of long hours.
RMT News spoke to a
member who has witnessed all
of these problems first hand.
After working 30 years as a
permanent employee he has
been forced into becoming an
agency worker on Network Rail
contracts.
“I was appalled at the chaotic
nature of how the site was run
with several engineering
supervisors overseeing workers
from several different agencies,
none of whom i had ever seen
before.
“These ES’s were shouting
differing instructions at us and,
having been told to undertake a
task from one only to be told to
do something else by another,
we were verbally abused by the
original ES for failing to
complete his instructions.
“The calibre and competence
of many of the agency staff on
what was a simple stressing job
was frightening and there was
even twice the number of staff
than was really needed if those
on site were either competent
and or interested in the job,”