Searchable article text
On 31 December 2002 the
private consortium Tube Lines
assumed responsibility for the
engineering functions on the
Jubilee, Northern and Piccadilly
Lines.
Engineering functions on the
remaining London Underground
lines were passed to the
Metronet BCV (Bakerloo,
Central, Victoria) and Metronet
SSL (all other LU lines)
consortia on April 4 2003. The
companies that make up the
private consortia are;
•
Metronet - Atkins, Balfour
Beatty, Bombardier
Transportation, EDF Energy,
RWE Thames Water
•
Tube Lines - Amey and
Bechtel
OPPOSITION
Before the Public-Private
Partnership was introduced
politicians, trade-unions,
transport users and transport
specialists were convinced that
the scheme would not work.
In September 2000 the
Industrial Society report, The
London Underground Public
Private Partnership, An
Independent Review, explained
that the PPP was offering a
guaranteed 15.3 per cent return
on equity for 30 years with
benchmarks for performance set
five per cent below the levels
expected of the publicly owned
London Underground.
The report concluded “that
the PPP should not proceed
unless it passes the re-specified
Public Sector Comparator we
have outlined. In other words
the PPP should go forward only
if it meets much more vigorous
safety and value-for-money
criteria, and if it is substantially
amended to protect against the
risk that the contracts are
incomplete and overgenerous. If
it fails to meet these criteria,
then the bidding companies
should instead bid for turnkey
projects funded and financed by
LUL within the public sector. In
the interim, this should be
undertaken through orthodox
Treasury financing, while the
preparation begins for London
to undertake its own bond
issues.”
In February 2002 the House
of Commons Transport, Local
Government and the Regions
Select Committee report, London
Underground, concluded “that it
is inevitable that the PPP will
lead to significant and
expensive disputes over the
contracts and between staff and
employers”. The report went on
to explain that “The initial
forecasts that the PPP would
provide a saving of £4.5 billion
over public sector management
were inadequate and flawed”.
Transport for London also
maintained that government
should not sign the PPP because
the scheme was not value for
money, it was unsafe and
unmanageable and the proposed
contract terms did not properly
protect the public interest.
The government chose to
ignore the warnings and
concerted campaigning and
imposed the PPP against the
wishes of the vast majority of
Londoners.
The results have been in line
with the fears and concerns
raised pre-transfer by the
opponents of the scheme.
By July 2006, Metronet and
Tube Lines had been paid £3.3
billion in performance-adjusted
Infrastructure Service Charge.
Given this huge taxpayers’
subsidy it is little surprise that
the Infracos have generated
huge profits for their
shareholders.
Between 2003/04 and
2005/06 Metronet BCV,
Metronet SSL and Tube Lines
made pre-tax profits of £286
million (see Appendix A for
complete figures). Regrettably,
performance has not matched
profit margins. A catalogue of
no fewer than eight reports has
cast serious doubt on the PPP’s
ability to deliver the upgrade of
the London Underground in an
economic and efficient manner.
FAILURE
In June 2004, TfL published
London Underground and the
PPP – the first year. The report
identified that during 2003/04
“the Underground’s assets
continued to provide dramatic
demonstrations of their
inadequacy”.
The 2005 TfL report
explained that in 2003/04 it was
too early to judge the
performance of the PPP but
bluntly stated: “In short,
performance is not good enough
and is less than was promised”.
The report explained that
engineering overruns had
increased by some 35 per cent
on the first year and were
averaging more than one a
week. The overruns were often
caused by poor project planning
and execution.
The 2005/06 report explained
that London Underground had
issued a Corrective Action
Notice (CAN) to Tube Lines due
to “persistent poor performance”
on the Northern Line which
“was manifest in repeated track,
signal and rolling stock
failures”.
In relation to Metronet the
late delivery of only 14 of the
35 station upgrades and the
incorrect preparation of District
Line tracks for summer
temperatures and disruptive
incidents on the Victoria and
Central Lines “undermine the
progress Metronet is making
and our confidence in the
capability of Metronet’s
management.”
The report goes on to say
that the upgrade of the Waterloo
and City Line “is an acid-test of
Metronet’s capability to manage
major projects”. In the event the
Waterloo and City Line re-
opened over a week late on 11
September 2006, exposing
Metronet to fines for the late
completion of works.
The line has since been
closed twice due to dust and dirt
caused by on-going engineering
works causing visibility
problems for train operators.
In June 2004 the National
Audit Office published two
reports into the PPP. The London
Underground PPP: Were they
good deals? detailed the PPP’s
huge start-up costs including
£109 million spent by London
Underground (LU) on external
advisors and £275 million paid
by LU to reimburse private-
sector bidder costs.
The report went on to say
that final PPP costs remained
uncertain. Not known for its
radical language, the NAO
states: “…there is only limited
assurance that the price that
would be paid to the private
sector is reasonable”.
June 2005 saw the
publication of the GLA
Transport Committee’s report
The PPP: Two Years In. Whilst
recognising strong performance
on the Piccadilly and Central
Lines the Chair’s foreword found
“…poor performance on the
Northern Line has led to Tube
Lines’ proposals to close
sections so that work can be
carried out to repair track and
signalling. On some lines the
programme for track and station
renewal is running behind
schedule”.
In March 2005 the House of
Commons Transport Select
Committee published their
RMTnews :: january 2007 :: www.rmt.org.uk
16
PPP–FOUR YEARS ON
RMT News looks back at
the chaos PPP has
brought to London
Underground