Searchable article text
A
CONTRACTOR was seriously injured earlier this
year when he was forced to jump from a moving
road rail vehicle (RRV) trailer during weekend
engineering works near Hayle Station in Cornwall.
A Rail Safety and Standards Board inquiry revealed long
hours of work, a failure to disseminate the lessons from a
previous accident, poor aftercare and a widespread habit
by the industry of turning a blind eye to the dangerous
practice of riding on vehicles not equipped for that
purpose.
The underlying cause of the accident began when the
plant access point was moved some four miles from the
work site without making provision for transporting staff
between the two locations. Two road rail vehicles with flat
bed trailers attached were used to take equipment back to
the plant compound adjoining the access point. While each
vehicle had a machine operator and a machine controller in
accord with the rules, neither RRV had a second seat.
On arrival at the access point the equipment was
offloaded into the compound. A ballast brush was then
loaded onto one trailer still attached to the remaining RRV,
as it was known that this piece of equipment was going to
be required later in the work plan. It was loaded unsecured
across the width of the trailer, which meant that the
spindles protruding from the sides overhung the trailer.
All three staff then positioned themselves on the
remaining trailer alongside the ballast brush for the journey
back to the worksite. It was estimated that the RRV, which
was now pushing the trailer, covered most of the journey at
a speed of between 10 and 15 mph, even though the trailer
is restricted to a maximum speed of 5 mph. However, as
there is no speedometer on these RRVs, the operator has
to rely on his own judgement.
On entering Hayle station the overhanging ballast brush
struck the platform ramp and began to lift and slew. The
three men riding on the trailer leapt onto the track, but as
the machine controller from the second RRV was about to
jump, he stumbled and fell. He was hit by the front road
wheels and run over by the rear road wheels as the RRV
passed over him. It was immediately clear that he was
seriously injured and was taken to hospital by air
ambulance.
Long hours
The inquiry discovered that the RRV machine operator
involved in the accident had left his home near Portsmouth
at 23:00 hours on Saturday night and drove to Hayle
overnight. He arrived at about 03:00 hours and then slept in
his van before reporting to the signing on point at 05:45
hours. Following the accident, he was required to remain
on the site in order to ultimately remove the RRV as he was
at the time the only machine operator available. He finally
left the site at around 19:00 hours, and while he was
offered a lift, he chose to drive himself home, arriving at
about midnight.
The other machine operator, who was one of those
standing on the trailer, was rostered to work from 06:00
hours until 18:00 hours on the Saturday, but in the event
worked until 22:30 hours to complete the work. He was
then called out next morning to work from 06:15 as only
one machine operator had reported for duty. After the
accident, he chose to drive himself to hospital to have ten
stitches in a cut hand which he sustained when he leapt
LAST February four RMT members were killed when a
runaway trailer from a poorly maintained road-rail vehicle,
owned by a private contractor, ploughed into a gang of
infrastructure workers at Tebay in Cumbria.
Despite numerous safety recommendations, two road-
rail vehicles (RRVs) were involved in potentially lethal run-
away incidents at the same Stockport site in the space of
two weeks last month. The site is part of the West Coast
Mainline renewal project, involving a number of contrac-
tors and sub-contractors. There was also a similar run-
away at Sheidmuir near Motherwell in May.
As a result, RMT has urged Network Rail to bring track
renewals back in-house for safety’s sake. The company
recently triumphantly released figures showing that
delays have delays in some areas fell by as much as 50
per cent in Wessex and the East Midlands where mainte-
nance was first taken in-house.
NR Deputy Chief Executive Iain Coucher said: “Network
Rail delays fell by almost 30 per cent in July, making it ten
straight months of sustained improvement. It’s the pas-
senger and freight users who benefit from this improve-
ment but there is still much more to be done”.
RMT general secretary Bob Crow agreed and said that
it was shocking to learn so soon after the deaths of four
RMT members at Tebay that there had been two more
runaway incidents this month under renewal contracts
which are still being handled by private contractors.
“What is even more disturbing is that the incidents, two
weeks apart, appear to have happened in similar circum-
stances on the same site and could so easily have
claimed more lives.
“After the Tebay tragedy we called for an inquiry into
safety standards in the fragmented, privatised rail indus-
try. So far we have had no inquiry, but the runaway inci-
dents have kept on happening. It seems that safety is still
taking second place to profit,” he said.
Bring track renewals back in-house
RMT has written to Network Rail expressing deep con-
cern and asking why the first of the two Stockport inci-
dents was not even mentioned at a recent meeting of the
Safety Council.
The exact causes of these two incidents will be estab-
lished by a formal inquiry into them, but it is clear that
Network Rail needs to take urgent action to control the
risk of runaways by improving site management and
ensuring the competency of machine operators.
“The most efficient way for Network Rail to gain proper
control over the assets and skills needed for the renewal
of the infrastructure is to follow its own lead and bring
track renewals back in-house, as it has already done
with maintenance,” Bob Crow said.
14
Remember Tebay? –
it’s still happening
‘Management turned a blind eye to a
practice they knew was prevalent in
order for the workload to be achieved’
from the trailer. He was at the hospital for some three hours,
after which he drove himself home, arriving at about 21:30
hours.
He told the inquiry that his employer had assessed him for
working the extra shift on Sunday, but it was common for
excess hours to be worked, especially by machine operators.
A blind eye
However, the Inquiry seemed satisfied that the employer had
appropriate policies and procedures to control excessive
hours. They seemed unconcerned that these policies and
procedures permitted him to work over 16 hours on the
Saturday followed by a short rest period of less than eight
hours before resuming another 12-hour duty. Neither did they
make any comment about the fact that having been involved
in a serious accident, he was then allowed to drive himself to
hospital with an injured hand, and from there to his home
over 200 miles away, where he arrived some 15 hours after
commencing work.
The inquiry identified the unauthorised riding on RRVs and
trailers. It is well known amongst staff that it was not
permitted but, as one of the machine operators stated, it is
common practice especially when there are long distances
involved as no other mode of transport was available.
Management also often turned a blind eye to a practice they
knew was prevalent but should not be condoned in order for
the workload to be achieved.
The inquiry recommended that during the possession
planning process, every effort should be made to minimise
the length of work sites, and in particular define plant access
points that are as close as practical to the actual work site.
Where long distances exist between the two points,
arrangements should include provision for the safe
conveyance of staff.
An examination of the signing on/off
sheets for the work also revealed a
poor level of compliance. The
inquiry felt it was difficult to see
how some individuals could
have received any site access
or safety briefings from the site
access controller. Also, even
where the staff did sign on, very
few signed off. This meant that it
would have been difficult to
ascertain who was accounted for if
there had been a more widespread incident.
15
Turning a blind eye
- a case in point
‘A Rail Safety and
Standards Board
inquiry revealed
long hours of work
and a failure to
disseminate the
lessons from a
previous accident’
A BLIND EYE: Staff inspect the point where an unsecured ballot brush, being transported by the Road Rail Vehicle, hit the platform at Hayle station and caused serious injuries